The Finery construction update

Mirvac is pleased to report that construction of The Finery at Waterloo has commenced and has reached important milestones.

The excavation and foundations of the basement structure are now fully complete. In addition, the tower crane has been installed and its operation has allowed the structural works to advance at a well-paced rate. The construction progress is gaining momentum and we have now completed 90% of the basement concrete slabs on ground.

Furthermore, the first suspended slabs have been poured and form-workers are already carrying out works to commence the ground floor slab. At this stage, there are over 100 staff working on the site daily and we expect to have more than 20 additional staff members each week until reaching maximum capacity.

The construction of the main building will soon commence and in the following weeks we expect to be seeing above ground structural works in progress.

We are very excited with the progress we have made and will continue to provide updates in the months to come.